Fill in the blank with the appropriate word. When activities are logically linked, they become the__________
Examine the figure given below:
If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?
A. Three days
B. One day
C. Four days
D. Zero days
You work as a project manager for BlueWell Inc. Your project is falling behind though the project team reports that the actual durations of their work is what they estimated. You investigate the cause and determine that the project team is not starting their assignments early enough to finish their work on time. While the duration of the assignments may be in synchronization with the duration estimates, the completion time is causing the project schedule to slip from the baseline. What can you do to rectify this problem?
A. Increase the duration estimates for each activity.
B. Discipline the project team.
C. Add management reserve.
D. Corrective actions.
You are the project manager for the NHQ Project. Management has asked you to create a time estimate for this project although you have only just received the project charter. They would like some idea of how long the project will take based on the information in the project charter. While you are uncomfortable giving any type of estimate at this point, you work with your assigned project to create a quick time estimate. What type of estimate have you created for management?
A. Analogous estimate
B. Broad estimate
C. Rough order of magnitude
D. Expert judgment
You work as a Project Manager for Tech Perfect Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:
What will be the cost variance (CV) of the project at the current point of time?
A. +80
B. -80
C. -10
D. +10
Which of the following techniques is used in businesses to determine the effect different costs or investments have on profit and other financial indicators?
A. Schedule analysis
B. Resource leveling
C. What-if scenario analysis
D. Root cause analysis
Virginia is the project manager for her company. She has used a previous project as a basis for her current project because they are similar in nature. Virginia has adapted nearly all of the previous project plans for her current project including the project schedule, risk register, and communications management plan. She has worked with management to update the plans to adapt them to the current project. What are the previous project management plans called in this instance?
A. Expert judgment
B. Analogous estimate
C. Templates
D. Parametric estimate
You have created the project network diagram for your project. Management is reviewing the network diagram and they are curious as to why you have included levels of effort activities as start-to-start and finish-to-finish successor activities for work that uses particular manufacturing equipment. You explained that the levels of effort activities are maintained for the equipment. This relationship and scheduling scenario is also known as what term?
A. Project management overhead
B. Hammock activity
C. Subproject
D. Finish-to-Start
You are the project manager for your organization. You want to record some details about the work that the project team has to complete. You want to document the level of effort, where the work is to be performed, and the person who will be responsible for completing the work. Which of the following is the best place to document this information?
A. Activity attributes
B. Project management plan
C. Schedule Management Plan
D. Roles and Responsibilities Matrix
Which of the following provides a method to track project progress during project execution against what was planned?
A. Team members profile
B. Benefit-cost ratio
C. Schedule baseline
D. Detailed project budget