A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the

communicated expectations.

Which of the following tools should the project manager use to validate the functionality?

A. Project status report

B. Requirements Traceability Matrix

C. Detect log

D. Signed project charter

E. Work breakdown structure

Buy Now
Questions 5

A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project. Which of the following should the project manager do next?

A. Buy a replacement for the faulty equipment.

B. Get the maintenance team to resolve the issue.

C. Escalate the issue to the project sponsor.

D. Rate the severity of the impact the issue has on the project.

Buy Now
Questions 6

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

A. Schedule

B. Status report

C. Issue log

D. Task board

Buy Now
Questions 7

Which of the following requires the MOST availability from the business team?

A. SDLC

B. Scrum

C. PRINCE2

D. Waterfall

Buy Now
Questions 8

A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?

A. SOW

B. RFI

C. RFQ

D. WBS

Buy Now
Questions 9

During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?

A. A risk budget

B. A risk impact

C. A change request

D. A contingency plan

Buy Now
Questions 10

A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?

A. Milestone

B. Gantt

C. Burndown

D. PERT

Buy Now
Questions 11

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

A. Pareto chart

B. Milestone chart

C. Burndown chart

D. Gantt chart

Buy Now
Questions 12

A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

A. 9 days and $3,000

B. 10 days and $3,200

C. 12 days and $3,800

D. 14 days and $4,000

Buy Now
Questions 13

Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?

A. Data security

B. Operational security

C. Physical security

D. Digital security