Sprint planning should result in a commitment on what will be delivered at the end of the Sprint. Who makes this commitment?
A. The Product Owner
B. The Scrum Master
C. The team
Under what circumstances would a team use Affinity Estimation Technique instead of Planning Poker?
A. If more details are needed during Sprint Planning
B. If there is a large number of stories to estimate
C. If there is a small number of stories to estimate
What is the objective of the Scrum-of-Scrums meeting?
A. To inform management about the progress of the project.
B. Bring together all team members of all teams.
C. Coordinate the work of multiple Scrum teams.
D. Kick-off an international Scrum project.
According to Agile principles, what should be the pace of development?
A. Fast
B. Increasing
C. Sustainable
What is time-boxing?
A. A period of intense activity within a particular release.
B. Setting an upper time limit and planning the activities within that limit.
C. Tight planning focused on reducing the time required for any activity.
A user story was estimated at five ideal hours. On a normal eight hour working day, the team gets about four hours of actual work time.
What would be the elapsed time required to complete the Story?
A. One day and two hours
B. Two days
C. Five hours
Why does the Daily Scrum need to be held at the same location and time?
A. The booking of a room needs to be done in advance for the duration of the Sprint.
B. The constant time and place is best for continuity of the Scrum framework.
C. The Project Manager needs to get the status updates at a given time every day.
What is a Scrum-of-Scrums?
A. A meeting for management to get insight into the working of teams.
B. A meeting for Scrum Masters of international Scrum teams.
C. A meeting to coordinate the work of multiple Scrum teams.
D. A meeting to show the customer an update of the product.
A team selects a Product Backlog Item (PBI) for the Sprint Backlog. What must a team do to finish the Product Backlog Item it selects?
A. As much as can be done in the Sprint before the deadline.
B. As much as is required to satisfy the definition of 'done'.
C. Analyze, design, program, test and document the PBI.
What is the expected outcome of the first Sprint on a project?
A. A few working, tested features from the Product Backlog
B. Architecture and high-level design of the Product
C. Assignment of the team, Product Owner and Scrum Master
D. A well-defined release plan for the Product