You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question
A. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"
B. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"
C. You can always maintain the actual start and finish date of a WBS element
D. You can only maintain the actual start of a WBS element if the finish date is not maintained
How can you grant individual authorization for WBS elements and networks?
A. Define a user status to lock the business transaction Update Project.
B. Set the system status to "Lock Master Data".
C. Activate access control lists (ACL) for the user master record.
D. Activate access control lists (ACL) for the project profile and the network profile
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order.
What do you have to consider?
A. The maintenance orders must be assigned to WBS element.
B. The maintenance order s must be assigned to the same budget profile as the project definition.
C. The maintenance orders must be assigned as sub-networks.
D. The maintenance orders must be assigned to the same plant as the network.
Float time is calculated during scheduling.
Which of the following statements about float time are correct?
Note: There are 3 correct answers to this question
A. Float time can be negative
B. Activities with the time constraint "Must start on" always have a negative float time
C. The float time of WBS elements is calculated by extrapolation
D. By default, critical activities have a float time, which is less than or equal to zero
E. The maximum size of a free float is as large as the total float of an activity
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?
A. Only capacity requirements
B. Forward
C. Current date
D. Backward
Cost and budget
A customer works in a multinivel production environment with bill of material and routing.
To avoid unnecessary stock cost, they do not want to produce.
Which setup do you recommend?
A. Assign a sales order to a project with appropriate hierarchy levels.
B. Assign a network to a sales order
C. Assign Several production orders to a sales order
D. Assign One production order to a sales order
Which of the following apply to dynamic item processor (DIP)? Note: There are 3correct answers to this question.
A. Usage of cost elements is mandatory
B. Sales prices are maintained in the DIP profile
C. DIP is used to create a quotation
D. Sources can be based on line items
E. Material determination is mandatory
You are working with networks and WBS elements. Which of the following statements applies
A. You can reassign an activity from one network to another
B. You can assign the network header to multiple WBS elements
C. You have to maintain a network profile in the project profile
D. You have to activate the operative indicator Account Assignment Element for WBS element with activities.
What are some of the possible functions in user status profiles? Note: There are 2 correct answers to this question.
A. Ensure user status must always be set manually
B. Allow business processes forbidden by SAP system status
C. Restrict setting user status for individual users
D. Utilize priorities for setting the user status
Which statement is valid regarding networks?
A. A network activity can be assigned to several WBS elements
B. Material components can be assigned to activity elements
C. Relationships can be used to connect activities of different networks
D. A network can be activity-account-assigned and header-account-assigned