Which activity type in resource planning enables you to define service specifications and value limits for
unplanned services rendered by the service provider? Please choose the correct answer.
Response:
A. Internally-processed activities
B. Externally-processed activities
C. Service activities
D. Scheduled activities
Which item category do you choose if you do not want to include the components in inventory management but want to use them immediately in the network? Please choose the correct answer. Response:
A. Stock item
B. Network item
C. Non-stock item
D. Procurement item
E. Answer: C
In resource-related billing if you do not want to bill a customer for a dynamic item, where do you enter this
information?
Please choose the correct answer.
Response:
A. You can enter in an apportionment reason
B. You can enter in reason code
C. You can enter in reference code
D. You can enter in reason for rejection
Which of the following helps you to adjust cost planning to changing circumstances during the execution
phase of the project?
Please choose the correct answer.
A. Progress analysis
B. Overhead costs
C. Interest forecast
D. Cost forecasts
Externally processed activities give rise to planned costs that are equivalent to the prices of the following? There are 2 correct answers to this question.
A. Actual costs
B. Purchasing Info records
C. Price in the activity
D. Services costs
If the available user-definable fields do not satisfy your requirement, you have an option to develop
additional fields for which of the following.
There are 2 correct answers to this question.
A. WBS elements
B. Activities
C. Project definition
D. Tasks
Assume a scenario where deviations from the project plan occurred as a result of delivery problems, price fluctuations, and unforeseeable capacity bottlenecks. How do you ensure that claims resulting from deviations are prepared for contractual partners and submitted to them at suitable point of time? Please choose the correct answer. Response:
A. Safety measures
B. Status management
C. Claim management
D. Actions
Which indicator do you use to define the characteristics of a WBS element and to specify tasks that are performed by the WBS element when the project is executed? Please choose the correct answer. Response:
A. Cost indicators
B. Project cost indicators
C. Operative indicators
D. Billing indicators
Among the various functions provided by progress tracking that simplify data entry and analysis which
function allows you to go the master data display for objects that are underlined? Please choose the
correct answer.
Response:
A. Mass change of scenarios
B. Copying dates
C. Subitems
D. Hotspots