A Physical % complete activity has an original duration of 10, and a remaining duration of 10. The actual start is assigned to the activity. Physical % is updated to equal 80%. What is the remaining duration for this activity?
A. 80
B. 10
C. 2
D. 8
You are an application administrator. You have been asked by your CEO to simplify the user interface for executives like her who are interested in high level summary information. Identify two ways to satisfy this request.
A. Customize the toolbar in a saved view.
B. Customize the EPS In a global view.
C. Customize security In the OBS.
D. Customize the Details fields in the Activity view.
E. Customize the menu bars in a saved view.
What are two benefits of designating a resource as inactive?
A. All project history and costs are retained.
B. Budgets from past projects will remain intact.
C. The associated user's information will be automatically deleted.
D. Actual costs for past projects will be positively affected.
E. The resource is identified as unable to perform future work.
Identify the true statement regarding administrative functions in P6 R8.
A. Administrative functions can be performed in the client, or in the web interface.
B. Administrative functions can only be performed in the client.
C. Administrative functions can only be performed in the web interface.
D. Administrative functions are determined at point of Installation.
What is the significance of setting "Summarize project based on high-level resource planning"?
A. Summarized project data will reflect top-down plans.
B. Summarized project data will reflect bottoms-up plans.
C. Summarized project data will reflect actuals pushed from another application.
D. Summarized project data will be monetized.
Identify two ways of quickly creating templates.
A. Create a template from an existing project.
B. Copy/paste existing project into templates node.
C. User Project Architect to modify templates.
D. Create complexity formulas to modify templates.
E. Base a new template on an existing template.
You are in a governance organization that has established a project management methodology with work product and document requirements that must be included in every project. You want to create s global activity view that includes a filter to show only activities that have required work products and documents as per the methodology. Identify three actions that would help you to accomplish this.
A. Create a Secure Global Activity Code.
B. Create a Global Security Privilege for the Governance organization.
C. Create a Global Governance Activity view.
D. Group and sort by Governance deliverable.
E. Create a filter available to the Governance organization.
F. Create a custom portlet for a Governance dashboard.
You are a program manager reviewing portfolio performance data. You see that many issues are assigned to a "responsible manager." What does "responsible manager" mean with Primavera P6 EPPM?
A. The person responsible for resolving the issue
B. The person who identified the issue
C. The element from the OBS associated with the issue
D. the manager to which the issue has been assigned
Identify three types of activity codes.
A. Global
B. Activity
C. Project
D. EPS
E. WBS
F. Resource
Select the true statement regarding project security profiles.
A. Project security profiles define the weight of project codes.
B. To receive a project security profile, a user must be defined as a resource.
C. Project security profiles override global security profiles.
D. To access projects, a user must be assigned a project security profile.